Sound insulation and underfloor heating as a single system, designed with tomorrow’s demolition in mind
An overview of the project
The new Road Traffic Authority building is being constructed in Viersen alongside a special needs school and a district archive as a new urban development complex, designed according to the principle of circular value creation. Wolf Bavaria planned and installed the entire underfloor heating system for the Förderzentrum West and the Road Traffic Authority, coordinating the installation with the building works on a room-by-room and heating circuit-by-circuit basis over an eight-month period of planning support.
Key figures: 441 heating circuits planned · 8 months of planning support · 950 tonnes of CO₂ equivalents sequestered over 30 years · 125 mm pipe spacing, throughout
Circular construction as a guiding principle
Built to be undone
The Förderzentrum West and the Road Traffic Authority have not only been designed as sustainable timber constructions, but also in line with an integrated approach encompassing material selection, dismantlability, reuse and carbon footprint. This guiding principle shapes every decision regarding the building components and materials, and it is precisely here that dry, demountable and acoustically efficient constructions such as PhoneStar and PowerFloor fit almost perfectly into the project’s logic.
Building according to the principle of circular value creation: building components and structures are consistently designed with a focus on demountability, reusability and recyclability.
Circular value creation
Components assessed in terms of dismantlability, reusability and recyclability
Objective: single-material, dismantlable and reusable structures
Critical composite materials are avoided wherever possible
Ecology and CO₂ approach
Timber structural framework as a key element of CO₂ sequestration
Approx. 950 t of CO₂ equivalents will be sequestered over 30 years
Project designed to be climate-neutral to climate-positive, with C2C and DGNB certification
Materials and Construction Methods
Focus on timber construction
Prefabricated, dry, demountable construction methods as the load-bearing principle
PhoneStar and PowerFloor consist primarily of paper and sand
Energy and building concept
Building with no connection to fossil fuels
Sustainability considered in terms of material selection, operation and energy supply
Surface heating as a low-temperature, efficient heat distribution system
Why Wolf Bavaria
Dry, detachable, high-performance structures
The circular project logic of Förderzentrum West and the Road Traffic Authority calls for systems that can be dismantled, separated and verified. This is precisely where Wolf Bavaria comes in.
Dry, demountable and acoustically efficient structures fit almost perfectly with the circular project logic.
Wolf Bavaria’s products are designed with the environment in mind; the core materials are primarily paper and sand.
Together with our partner Cemwood, we have demonstrated that the high live loads of up to 5 kN/m² required for commercial buildings in accordance with DIN EN 1991-1-1 can also be achieved using a dry screed system.
Using PhoneStar, compliance with the sound insulation requirements relevant under building regulations has been mathematically verified.
Together with PowerFloor, this creates an environmentally sound, resource-efficient and recyclable system construction solution from a single source.
Quiet paths for everyone, including those with a tactile paving system
A particular challenge with impact noise
The challenge
Accessibility guidance systems consist of tactile elements such as studs and ridges, which can be felt by the fingers or a white cane. It is precisely these elements that pose an acoustic challenge: when a cane passes over the guide strips, the impact noise can be transmitted undamped through the terrazzo floor into the rooms below; in the case of continuous corridors and multiple storeys, this is a problem that would have been clearly audible without effective sound insulation.
The solution
Wolf Bavaria provided advisory support to the flooring contractor, zebo, during the installation of the impact sound insulation system beneath the terrazzo. The PhoneStar system, specially developed for effective impact sound insulation beneath hard floor coverings, was used; Sales Manager Christian Pongratz oversaw the project right through to final acceptance, which was completed without any objections.
Silence is the aspiration that drives us every day.
Quiet corridors, even when the guidance system is in use
zebo Fussbodenbau is one of those companies that delivers reliability even on demanding large-scale public projects. For the new Road Traffic Authority building, zebo – represented by its managing directors Philipp Frensch and Wolfgang Frensch – undertook the laying of terrazzo floors throughout the building, as well as the installation of the tactile accessibility guidance system, complete with studded and ribbed patterns for long white canes and guide sticks.
Wolf Bavaria provided consultancy support regarding the impact sound insulation beneath the flooring, ensuring that the quality of workmanship and adherence to the schedule were both met for an administrative building of this scale.
"In a project of this scale, impact sound insulation simply has to work, particularly beneath the signage system. With PhoneStar and the support of Wolf Bavaria, we were able to resolve this neatly and on schedule."
The underfloor heating also works reliably:
Planning down to the last centimetre
Each heating circuit was planned individually: pipe routing, pipe length accurate to the centimetre, and allocation to the appropriate roll of pipe. The colour-coded installation plans provide the installation team on site with a clear correspondence between room, heating circuit and manifold, across both buildings and all five storeys.
System used
Wolf PowerFloor Light, pipe spacing consistently 125 mm
Adhesive systems depending on the subfloor: Wolf system adhesive and Wolf roll-on adhesive on timber or PhoneStar subfloors; Wolf 1K parquet adhesive with TKB B11 notched trowel on mineral subfloors
Elements without a groove and with aluminium sheeting in marked areas; additional groove milling using a hand-held router where heating pipes cross
Predominantly the ‘Light’ system variant (14 mm milling diameter); in some areas, the ‘ÖkoPlus’ variant (16 mm milling diameter)
Coordination with other trades
Co-ordinated installation around numerous decentralised ventilation units (master and slave units) in several rooms in both buildings
Inclusion of a split-system indoor unit (5 kW) in the SVA building
Distribution cabinets provided both as surface-mounted solutions (AP 12) and as pre-wall solutions with an access opening measuring 800 x 600 mm
Wall penetrations and the heating output per room were cross-checked prior to installation, as noted in the installation plans
Full version of this success story
How exactly did that work?
How much did it cost?
What was the contractor’s profit margin?
Was the sound insulation tested?
You can easily download the full version of this success story and the project profile here. It also includes further information not listed here, such as the exact structure, etc.
Why are we asking for your details?
We’re happy to share our knowledge – but not entirely on the open internet. In this age of AI and automated data extraction, we don’t want 20 years’ worth of soundproofing expertise to end up freely accessible somewhere online. That’s why you won’t get our story at the click of a button, but through an exchange: your contact details in return for our knowledge. We’re already revealing part of it here; if you’d like to know more, you’ll need to strike a deal.
What happens to your data
We know what your data is worth – just as we know what our expertise is worth. A fair exchange, in our view. We use your details to send you the story and to advise you personally on any questions you may have about your project. Nothing is passed on to third parties.
Feel free to download the story.